Given that the world’s top rated column-based industry knowledge storage facility, through SAP much more than three, 100 people on much more than contemplate, 000 undertakings around the globe, Sybase IQ supplies a lot quicker, alot more legitimate gains designed for mission-critical internet business mind, knowledge warehousing, PASSLEADER predictive analytics and even reporting choices at trade traditional computer and even os’s to help you establishment across the country. In conjunction with C_TSCM42_66 dumps download BI concept as a result of SAP, Sybase IQ provides a well-rounded knowledge warehousing and even data store stage to get to know site visitor must have.

QUESTION 1
In which master data object do you set the standard values for an operation?

A. Material Master
B. Work Center
C. Routing
D. Production Resource/Tool (PRT)

Answer: C

QUESTION 2
What features related to process orders can be used to fulfill Good Manufacturing Practices (GMP) requirements? (Choose three)

A. Approved master recipes
B. Digital signature
C. Electronic batch record
D. Availability check
E. Resource selection

Answer: ABC

QUESTION 3
In the SAP ECC system, a material is produced using production orders. The planning table for repetitive manufacturing should be used to plan line loading for this material. On the initial screen of the planning table, you select this material and then receive a message informing you that you cannot use the planning table for this material (see attached screenshot). What could be the reason?

A. There are no planned orders or production orders present.
B. The repetitive manufacturing indicator has been set.
C. There is no valid production version for this material.
D. There are no requirements present.

Answer: C

QUESTION 4
Which activities lead to a reduction of the capacity requirements for an operation? (Choose three)

A. Rescheduling the operation
B. Posting the goods receipt for the production order
C. Confirming the operation
D. Setting the status technically complete (TECO)
E. Reducing the order quantity

Answer: CDE

QUESTION 5
Which property applies for consumption with planning strategy 40 (planning with final assembly)?

A. Consumption creates a static and binding assignment between the planned independent requirements and the customer requirements for the entire procurement process.
B. Consumption takes place with the planning material.
C. Consumption can reduce the total originally planned production quantity.
D. Consumption can increase the total originally planned production quantity.

Answer: D

QUESTION 6
Which of the following elements can be used in a process order? (Choose three)

A. Process instructions
B. Parallel sequences
C. Relationships
D. Suboperations
E. Phases

Answer: ACE

QUESTION 7
You want to create a new material that – is kept in stock- is externally procured- is used as a component in the bills of material for various final products- must not be sold directly. Which standard SAP material type do you use?

A. NLAG (non-stock material)
B. FERT (finished product)
C. ROH (raw material)
D. HAWA (trading good)

Answer: C